# **25 Pre-Concreting Checks Every Site Engineer Must Complete**
Based on your uploaded infographic, here are all 25 checks, arranged under the same five categories.
## **1. Drawings & Approvals (1–5)**
1\. **Latest Approved Drawings:** Latest approved structural drawings and relevant MEP drawings (where embedded services are involved) are available at site.
2\. **Concrete Grade & Mix Design:** Specified concrete grade (e.g., M20 / M25 / M30 etc.), approved mix design (or site mix as per specification) and requirements are verified.\
*Note: IS 456 specifies M20 as the minimum grade for RCC under normal conditions.*
3\. **Pouring Sequence:** Pouring sequence, construction joints and their approved locations are confirmed.
4\. **Method Statement & Safety:** Method statement and safety arrangements (PPE, access, fall protection, etc.) are approved and communicated.
5\. **Previous Inspection Clearance:** All previous inspection observations are resolved and required RFI approvals (Pre-Pour) are obtained.
## **2. Formwork & Shuttering (6–10)**
6\. Formwork is as per drawing, with correct alignment, level, dimensions, supports and bracing.
7\. Shuttering joints are tight and leak-proof to prevent cement grout leakage.
8\. Camber (where specified) is provided and required concrete cover is maintained using approved cover blocks.
9\. All inserts, sleeves, conduits, pipe openings and other embedded items are fixed and secured as per approved drawings.
10\. Formwork is clean, free from debris and standing water. Apply approved release agent (form oil) without contaminating reinforcement.
## **3. Reinforcement (11–15)**
11\. Verify reinforcement bar diameter, spacing, number and arrangement as per approved drawings.
12\. Check lap length, lap locations, anchorage and development length (Ld) as per approved structural drawings and IS 456 provisions.
13\. Reinforcement is clean and free from loose rust, mud, oil and other harmful contamination.
14\. Required cover blocks (material, size, type and spacing) are provided and stable.
15\. Reinforcement is properly tied, adequately supported and will not be displaced during concreting.
## **4. Materials & Resources (16–20)**
16\. Verify cement type (OPC/PPC/PSC), source, condition, storage and applicable test requirements (freshness, as per IS 269/IS 455).
17\. Aggregates (size, grading, quality) and sand (silt content) meet project specifications. Water quality shall conform to IS 456 requirements (potable water is generally suitable; non-potable water may be used if it meets IS 456).
18\. Approved concrete mix design (RMC or site mix) and trial mix results (where required) are available.
19\. Adequate skilled manpower, vibrators (with standby), tools and equipment are arranged.
20\. Concrete supply, transit time, delivery sequence and pumping arrangement (if any) are confirmed and coordinated.
## **5. Site Readiness & Quality Control (21–25)**
21\. Slump test equipment, cube moulds, sampling arrangements and curing facilities (tank, water, etc.) are ready.
22\. Adequate lighting arrangements are provided, especially for early morning or night concreting.
23\. Check weather conditions and arrange protective measures (e.g., rain protection, heat control or cold-weather concreting) as applicable.
24\. Brief the site team on QA/QC requirements, testing frequency (slump, cubes, etc.), inspection records and acceptance criteria.
25\. Final pre-pour inspection is completed and documented approval / pour clearance is obtained from the authorized engineer / consultant (PMC / Client).
## **Key takeaways**
- Use a pre-concreting checklist for every pour.
- Ensure compliance with approved drawings, specifications and IS codes (e.g., IS 456).
- Complete all QA/QC documentation before starting concreting.
- Take approvals and maintain proper inspection records.
Site Engineer Reminder
**DO NOT START CONCRETING** without completing the required checks, obtaining inspection clearance and documenting pour approval.
*Note: This is a transcription of the uploaded infographic, not an independent verification of the technical or code requirements.*